Pattaya Jomtien 2nd Road drainage project to wrap in April

0
2290
Work is in full swing along Thappraya Road from Mutchanu curve to Dongtan curve on Jomtien Beach.

Work to lay new drainage pipes under Jomtien Second Road between Rompho Market and the Dongtan Curve is on scheduled and should be finished next month, Pattaya Deputy Mayor Pattana Boonsawad said.

Flooding along Second Road should greatly reduce once the system is fully operational, Pattana told the media March 9.

The first phase of the project from Rompho Market to the Mutchanu (Hanuman) Curve had new pipes laid and cesspools installed before the road was resurfaced in concrete.

The second phase from Mutchanu to Dongtan Curve includes 450 meters of new pipe and concrete road resurfacing.

The 280-million-baht project should be complete by the end of April, the deputy mayor said.


New drainage pipes are laid and cesspools installed before the road was resurfaced in concrete.


The road will be surfaced with concrete. Work is expected to be completed by the end of April.