Long-delayed construction on
Soi Nernplabwan was finally completed.
Jetsada Homklin
Long-delayed construction on Soi Nernplabwan was completed five days
earlier than an estimate given last month.
Nongprue Sub-district Mayor Mai Chaiyanit said officials had received 7
million baht from Chonburi Province to finish the project originally slated
for completion on Sept. 6.
Residents in Roong Ruang village have complained bitterly that contractor
Promyothakan Rayong had left large holes in the road while workers went
missing. He announced on Oct. 27 work would be done on Nov. 10. It finished
on Nov. 5.
Krtisada Ketjinda, the coordinator between the contractor and Chonburi
Province, said Promyothakan Rayong claimed it couldn’t finish the work on
the original schedule due to continuous rainfall.
Promyothakan Rayong laid drainage pipes and covers, U-shaped pipe connectors
and resurfaced the street with ferro-concrete.