With Northpoint now a landmark on the Pattaya skyline,
construction through June continued to make strong progress.
The
Northpoint Towers stand tall over the Wong Amat coastline.
Site clearance and piling works to the “Zone A” landscape area between the front
of Tower A and the Wong-Amat Beachfront are still ongoing. The pile casting for
the main pools at the beachfront are now complete and reinforced concrete slabs
are being cast.
Mechanical, electrical and plumbing first fix installations have progressed
towards the penthouse levels of both towers, and the second fix installations
are progressing significantly at both towers to follow. The electrical busduct
installations are ongoing.
Permanent power and water supply applications have been progressed and are
expected to be connected at site according to programme. The passenger lift
installations are ongoing with designated lifts having now been tested,
commissioned, protected and handed over to the Main Contractor for temporary use
during the remaining works. Two of four external temporary passenger hoists have
been de-commissioned and removed from site accordingly.
Swimming
pools structural work in process.
The transformer building reinforced concrete roof slab has been cast and
associated waterproofing works completed.
Externally, the towers walls surface preparation and Lanko skim coat application
process is ongoing and the textured and flat paint decorative applications to
the façade are being progressed at both towers. Internal block work walls and
plastering have been substantially completed, followed closely by installation
of aluminium and glazing installations to the facade and balconies of the
buildings.
Imported floor and wall tiling installation works remain ongoing and have
significantly advanced at both towers, internal ceiling installations have
progressed equally, followed closely by kitchen fit-out and appliances
installations; built-in wardrobes installations; vanity units, joinery doors and
floors, and frameless shower cubicles.
Sanitary ware installations are also making good progress up the building at
site with deliveries ongoing to the site commensurate with installation
progress.
The main entrance lobby area to both towers are in the process of fit-out works
with general lift lobby and corridor area fit-out works also progressing within
the towers. (Source Raimon Land)